Resumption of Production Affected by The 2016 Kumamoto Earthquake

June 14, 2016, Japan

Corporate

June 14, 2016 - Honda resumed on May 6 at its Kumamoto Factory (Ozu-machi, Kikuchi-gun, Kumamoto Prefecture) which had been halted since the night of April 14 due to the effects of The 2016 Kumamoto Earthquake, component supply for overseas production facilities.

Honda has completed the removal of debris from, and damage assessment of, the most affected facilities such as the assembly plant, and partly resumed assembly of its main motorcycle models on June 6. Production initially resumed on a small-scale, although it will be increased in stages according to facility conditions, aiming towards a complete recovery in mid-August.

Honda is fully committed to continue its efforts towards a rapid recovery, and is grateful for its customers’ understanding.