Guangqi Honda to Build a Third Automobile Production Line

April 23, 2012, China

Corporate

BEIJING, China, April 23, 2012 - Guangqi Honda Automobile Co., Ltd. (GHAC), an automobile production and sales joint venture of Honda in China, today announced plans to build a third production line within the property of the existing ZengCheng Plant.

The construction of the third line will begin at the end of this year, and the line will become operational in 2014 with an initial annual production capacity of 120,000 units. GHAC is planning to further expand the capacity up to 240,000 units in the future. The new production line will be a highly-efficient and environmentally-responsible state-of-the-art line. GHAC is also planning to build a new engine plant in time for the start of production on the third line. The total investment for the third line (with capacity expandable up to 240,000 units) and the new engine plant is expected to be approximately 3.56 billion R.M.B. (approximately 46 billion yen*).

When the third line becomes operational in 2014, GHAC's overall annual automobile production capacity will be increased from the current 480,000 units to 600,000 units. In the meantime, Dongfeng Honda Automobile Co., Ltd., another Honda automobile production and sales joint venture in China, is scheduled to begin production at its newly built second plant in July of this year, increasing the company's annual production capacity to 360,000 units by 2013. With these capacity expansion measures, Honda's overall annual automobile production capacity in China will increase from the current 770,000 units to 1.01 million units in 2014. In addition to capacity expansion, Honda will further localize its R&D capabilities in China, the world's largest automobile market, to further strengthen its operation to deliver new products which focus on Chinese customers, with speed, affordability and low CO2 emissions.

  • *calculated with an exchange rate of 1 R.M.B.= 12.92 yen

<Reference> Honda's Annual Automobile Production Capacity in China

Plant / Line Line Current July 2012 2013 2014
Guangqi Honda
HuangPu Plant No.1 240,000 240,000 240,000 240,000
ZengCheng Plant No.2 240,000 240,000 240,000 240,000
No.3 - - - 120,000
TOTAL 480,000 480,000 480,000 600,000
Dongfeng Honda 1st Plant 240,000 240,000 240,000 240,000
2nd Plant - 100,000 120,000 120,000
  TOTAL 240,000 340,000 360,000 360,000
Honda Automobile (China) (export only) 50,000 50,000 50,000 50,000
TOTAL 770,000 870,000 890,000 1,010,000

【About Guangqi Honda Automobile Co., Ltd.】

Established: July 1998
Capital Investment: US$283.29 million
Capitalization Ratio:
50% Guangzhou Automobile Group Co., Ltd.
40% Honda Motor Co., Ltd.
10% Honda Motor (China) Investment Co., Ltd.
Location: Guangzhou City, Guangdong Province, China
Representative: Toshiaki Mikoshiba, President
Employment: Approximately 7,600 associates